βPriorityβ column cannot be changed
Click to sprint value in sprint cell, navigate to sprint page failed
Too many request error when saving after moving the ticket having a large number of children.
When editing priorities, the selection candidates are displayed according to the priority scheme settings.
Issue rows cannot be moved from directly under version to directly under project if user does not have "Issue Link" permission
The issue happen when
The issue type is higher than Epic in hierarchy configuration
And the issue level is higher than Epic (reproduced with Epic level = 1, the issue level = 2)
Reproduce steps
With premium site
Go to Jira issue config -> Issue type hierarchy tab
Create level
Add Jira Issue types into level higher Epic level -> Save Changes (Finish configuration)
Back to Gantt
Reproduce Steps
Team managed Project with Open Access level (any ones can create issue)
You are Jira Admin, but not Project Admin
You can create/update ticket in Jira
Open the default Gantt of the project.
Can not clone in to template
Can not create or manage the issue in the template
eproduce :
When there is a period (days or hours) in the "preceding task" in the mpp file
Execute "MS Project import" from the operation bar of the WBS Gantt-Chert view screen.
Expected : The value is in the "Lag" of the dependency of the created issue.
Observed : All the dependency "Lag" of the created issue is Null.
"Manage Gantt Scheme" button in create Gantt screen does not work
I want to display the Parent field that was replaced from Epic Link on the Gantt chart.
If the Team field is displayed on the Create Issue screen, creating an issue on WBS will fail.
The duration will be changed.
All cells are exported blank.
Currently Template Sharing is only for Company-managed Projects.
The Team-managed Projects are using their own issue type, so user will configure the issue type mapping when using template sharing between projects.
Remove the prefix when creating or copying issues
Reproduce step
Configure Gantt to calculate percent done by TimeTracking
Logwork for any issue in Gantt
Reload Gantt, the Save button is enabled, click Save
Open (or reload) Gantt again, the Save button is enable again.
Create a version with some issues inside
Uncheck βVersions related to issues onlyβ in gantt configuration, the version is shown well on gantt
Check βVersions related to issues onlyβ in gantt configuration, the version disappear on gantt
The position should be retained even after switching tabs.
"Browse Projects" has been deprecated.
https://community.atlassian.com/t5/Jira-articles/Announcement-Introducing-two-new-permissions-to-replace-Browse/ba-p/2108241
If the task for the day is existing, and the next day has task with 0% Units, it is displayed for the day in resource view
The ability to block Gantt-Chart reorder of Issues that are shared with other Gantt-Chart's. Currently, if you use two Gantt-Charts with the same Project/Filter, one Gantt-Chart re-order each other issues automatically.
It would be useful if the "Issue template share project" feature of the Server/DC version is also available in the Cloud version.
The week number that can currently be displayed is the U.S. style. It differs from the week number used in Europe.
It would be useful to have the ability to register some Gantt as a favorite, like Jira's starred filter.
If the Description field has more than 83 characters, it starts to overlap with the Gantt Bar and eventually overflows to the Assignee.
Unable to create issues.
There are some settings that we want to use in common for many Gantt.
Due to a bug, %done is calculated the way it was before the following improvement was implemented. https://portal.productboard.com/ricksoft-inc/5-wbs-gantt-chart-for-jira-cloud/c/71-done-of-a-project-be-based-on-issues-done?utm_medium=social&utm_source=portal_share
Jira will only store the value of a number field to the third decimal place. By adapting WBS Gantt-Chart specification to Jira specification, WBS Gantt-Chart can reduce the %done updates. However, if the value is 99.9995 or more but less than 100, it will be rounded down to the fourth decimal place.
When you use βDate Time Pickerβ custom field and export as Excel, the excel file does not contain the time. The column only has date.
It would be nice to have a button to direct the user to WGC on a Jira Project page.
Reproduce
Company managed project
A child issue of Epic(Story, Task) cannot be created. But a child issue of Task or Story can be created.
Cause
Jira API return booth parent and Epic link in response. Code logic is processing for response has either parent or Epic link. So get error in case of API return both.
It would be helpful to add Sprints directly to WBS Gantt-Chart Structure instead of only having the option to add the read only column.
It would be useful to have a shortcut in the app to easily go to the Gantt list page.
Units and Effort are unfamiliar words to Jira users, so please add a tip explaining what role columns they are.
It needs to be fixed to import the correct date.
Cloud migration will not complete.
Immediately after importing, the start and finish dates are displayed. However, those values are not stored in the issue field and will disappear when the user reloads the screen.
This feature is similar to the "Convert into template" feature in the Server/DC version. However, like "Convert into template", this does not convert issues in standard mode directly into a template. Make a copy of the issues and store it in an existing template or in a new template.
It would be good if Start and Finish dates of the project could be automatically set based on the minimum and maximum issues dates, just like parent issues are defined.
% Done of a project row could be based on the % done of project issues, just like it's used to calculate the parent issues.
Use Jira's fields as WBS Gantt-Chart Start Date and Finish Date.
Changing the format of the date picker in Jira system settings
Display the Start Date and Finish Date fields on the issue screen.
Under the above conditions, the MS Project import fails.
workaround Temporarily set the date picker format back to default. Or temporarily hide the start and finish date fields in the issue create screen.
% Done field doesn't get exported when task has 1 day duration
There are a number of task in gantt chart that is 1 day in duration. However, when they are exported to Excel, Excel shows those task as 0 days.
It would be nice if app supports more languages besides English.
Bug
This percent done is misleading to users.
The value of duration for each task may change before and after the data conversion is executed.
Issues with subtasks will not be shown even if they match the search criteria.
Create a new Project by using Project Management template. (Jira Core Template)
Create a Gantt-Chart from the project.
Create a child ticket from Gantt-Chart. The new issue does not have a Hierarchy link.
workaround
This bug occurs when "Linked issue" field is not registered in the "Create issue" screen.
You can work around this bug by adding Linked Issues field to the screen in the "Create issue" screen settings.
This problem occurs in Jira, where there are thousands of issue filters.
When the value of a cell is non-empty, editing will return the value to the value before editing. But, users can still edit the start date, end date, and duration by manipulating the Gantt bar.
Indenting the issue and saving, WBS is broken after reloading.
It would be nice to have the ability to show/create Predecessors and Successors in column. So that we can create dependency links without using the mouse dragging feature.
Currently dates fields are app's own data.
So, it cannot use in JQL, cannot set data by Jira standard way, cannot get data via Rest API and cannot integrate with another apps.
Make it be able to use any custom fields instead of app's own data.
In 1.1.15-AC and later versions, it is now possible to create hierarchy and dependency using issue links. Convert the hierarchy and dependency stored as unique data into issue links.
the Vertical divider can not be moved beyond a certain part of the screen.
Epics/Stories from Archived versions are displayed without any hierarchy/structure after update 1.1.15-AC.
It would be good if setting a dependency link through the Gantt-Chart, an issue linking in Jira would be established, just like at server platform. Same for epic links/child created though WBS Gantt-Chart for Jira.
It would be nice to be able to set the global holiday calendar as like WBS Gantt-Chart for Jira Server/DC.
Improve the narrow editing area, which makes it difficult to edit.